A line can run all shift and still miss its delivery commitment. A mine can hit its haulage target and still come up short on saleable tonnes. Takt makes the required pace explicit, so teams can see where measured performance falls short and where extra output would only build inventory.
Calculate the required pace
- Takt time = net available production time ÷ required good output.
- Takt rate = required good output ÷ net available production time.
Use demand and time from the same planning period. Deduct scheduled periods when production is unavailable, such as planned breaks or shutdowns. Keep unplanned losses visible in the performance comparison. If the planning model already deducts a loss from available time, avoid deducting that same loss again from the rate. Actual cycle time measures the observed pace. A planned cycle time is the pace you design for and may be shorter than takt to allow for variability.
Manufacturing case study
A packaging line has an eight-hour shift and 60 minutes of planned non-production time. Customers require 480 good units per shift. The line has 420 minutes available, so takt is 420 × 60 ÷ 480 = 52.5 seconds per good unit. The equivalent rate is 68.6 good units per available hour.
| Station | Before | After |
|---|---|---|
| Prepare | 46 | 46 |
| Fill | 60 | 50 |
| Inspect | 44 | 48 |
| Pack | 48 | 48 |
Filling took 7.5 seconds longer than takt and capped the serial line at about 420 good units per shift, 60 short of demand. The team models removing six seconds of repeat handling and moving a four-second label check from filling to inspection. Filling drops to 50 seconds and inspection rises to 48. At 50 seconds per good unit, modeled line capacity is 504 per shift, leaving 24 units of headroom. The release plan stays at 480. Confirm the new cycle times over several shifts, including representative stops, product mix and quality losses.
Mining case study
A coal value chain plans to deliver 9,600 saleable tonnes per day over 20 net system hours. System takt rate is 480 saleable t/h. At a 75% mass yield on a consistent measurement basis, the plant needs 9,600 ÷ 0.75 = 12,800 run-of-mine (ROM) tonnes per day. For this example, assume no net stockpile change, and equal plant feed and ROM deliveries over the day.
| Activity | Available hours | Required rate | Baseline rate |
|---|---|---|---|
| Loading (ROM) | 16 | 800 t/h | 830 t/h |
| Haulage (ROM) | 18 | 711.1 t/h | 680 t/h |
| Processing (saleable) | 20 | 480 t/h | 490 t/h |
Haulage is short by 560 ROM tonnes per day: 680 × 18 = 12,240 tonnes against 12,800 required. At 75% yield, that is 9,180 saleable tonnes per day, a shortfall of 420. Compare loading, haulage and processing in saleable tonnes per day to find the limiting activity. Their baseline equivalents are 9,960, 9,180 and 9,800 respectively.
Suppose dispatch changes reduce queueing and raise measured haulage to 740 ROM t/h over the same 18 hours. Haulage now supports 9,990 saleable tonnes per day at the assumed yield. Processing, at 9,800 saleable tonnes per day, becomes the lowest-capacity stage and leaves 200 tonnes of headroom over plan. Track yield, stockpile movement and actual operating hours each day. A lower yield or fewer haulage hours can reopen the shortfall. For example, 740 t/h needs about 17.3 haulage hours to move 12,800 ROM tonnes.
Use takt in the daily review
- Agree the output commitment, quality basis and time window before calculating the pace.
- Translate the system commitment into the units and available hours of each activity. Where relevant, use the mine plan to relate overburden movement to coal exposure and the required production period.
- Compare actual and required performance, then express each shortfall in finished units or saleable tonnes. Check stockpile and buffer movements before concluding that a stage is limiting delivery.
- Review the losses at the limiting stage, test a change, and recheck the whole chain. Reset takt when demand or the production window changes.
Takt sets the pace the business needs. Constraint analysis identifies what limits the system from achieving it. See the Theory of Constraints case study for more on identifying and managing the bottleneck.
The worked figures are teaching examples. The approach draws on Concept of Target/Takt Time and the activity-rate and common-metric approach in the supplied mining calculator.